Here are all the questions that a poor confused Raven can't winkle out from the available public information.  
+
Here some questions and assumptions a poor confused Raven has had to make due to lack of  information.  
  
*'''Equity''' - The bonds provided $165.4 million, and the GNWT appropriated another $15.9 million.  That pretty much equals the $181.4 million construction budget.  But there was [[INAC contribution|$1.4 million from the feds]] which was apparently transferred to the GNWT.
+
*'''Budget''' - there's no newer details on the construction budget (now around $192 million) since the original 2010 package that was released.
  
==Not yet made public==
+
*I'm assuming none of the '''additional $10 million''' announced in Dec 2011 will go bond payments or ferry/iceroad costs.  I'm also assuming that none of the costs below are included in it, either.
  
*new estimated opening date
+
* the '''capital costs of the tolling system''' will be at least $1 million, as previously indicated, for some sort of camera/electronic identification system.
*annual O&M for the bridge
+
 
*annual toll collection costs
+
* there is no public guidance on '''annual toll collection costs'''.  I'm assuming a few hundred thousand dollars a year until better info is available.
*final construction costs
+
 
 +
* there's no update on [[Annual Operating Costs|annual bridge O&M]] costs.
  
 
{{Incomplete}}
 
{{Incomplete}}

Revision as of 01:30, 15 December 2011

Here some questions and assumptions a poor confused Raven has had to make due to lack of information.

  • Budget - there's no newer details on the construction budget (now around $192 million) since the original 2010 package that was released.
  • I'm assuming none of the additional $10 million announced in Dec 2011 will go bond payments or ferry/iceroad costs. I'm also assuming that none of the costs below are included in it, either.
  • the capital costs of the tolling system will be at least $1 million, as previously indicated, for some sort of camera/electronic identification system.