Here some questions and assumptions a poor confused Raven has had to make due to lack of  information.  There's also [[DoT_document_hunt|a separate list of documents being looked for]].
+
There was a list of outstanding work on the bridge [http://www.assembly.gov.nt.ca/_live/documents/content/13-03-11TD48-17(4).pdf submitted to the Assembly], but it looks like it is all covered either by the construction budget/holdbacks or the NB $13 million fund.
  
 
==Current==
 
==Current==
=== 2005-2006 tenders and pricing ===
+
* Is the "current project budget" still at $202 million?
The GNWT timeline says:
+
* [http://documentcentre.eycan.com/eycm_library/Project%20Aqua%202/English/Motion%20Materials/17.%20Notice%20of%20Motion%20dated%20April%209,%202013/Atcon%20-%20Record%20on%20Motion%20dated%209%20April%202013.pdf Atcon $1.3 million settlement] payment - covered by project budget?  I'd assume so, like the Gamble/Jivkov settlement.
* October 2005 - project tendered, with one bidder.  Bid rejected due to price.
+
* Atcon deficiencies - current spend ($6.5 million?) and upcoming work ($3-5 million?)
* February 2006 - Project re-tendered. Price beyond pre-determined financial limits.  Project shelved.
+
* Fish Habitat Compensation Plan - any costs estimates?
 +
*Average annual O&M still around $350,000?
 +
*Average annual toll collection costs around $300,000?
  
However, from news stories of the time, I get:
+
* Any numbers on toll traffic?
* [http://www.nnsl.com/frames/newspapers/2005-11/nov7_05br.html Oct/Nov 2005] - project tendered, deadline Dec 6.
+
* [http://www.nnsl.com/frames/newspapers/2005-12/dec16_05dc.html Dec 2005] - tender deadline extended to Jan 20.
+
* [http://www.nnsl.com/frames/newspapers/2006-03/mar15_06brg.html Jan 2006] - tender deadline extended to March 22.
+
* March 2006 - presumably the tender(s) come back, way too high.
+
 
+
The Auditor General has:
+
* tendered in 2005, $179 million bid on Spronken design from someone (with a $149 million design-build alternative).
+
* "independent cost estimate" completed in 2006 at $155 million.
+
 
+
My reconciliation of this would be that there was a single tendering process, with extensions, from Oct 2005 through March 2006, which produced the $179 million/$149 million bid from someone (presumably SNC Lavalin or the Kiewit/American combo) no earlier than March 2006.  There was no "re-tender" in February, although that might refer to the deadline extensions.  Somewhere in 2006 there was some sort of non-tender pricing exercise (by who?) that produced the $155 million number.
+
Whatever they may have feared, the first time DCBC would have had to admit to a triple-digit number would have been 2006 - no bids came back to be "rejected in Oct 2005".
+
 
+
===Equity===
+
Now that [[Gamble-Jivkov lawsuit|Gamble-Jivkov]] is settled, I was going to see if I could make sure of the DCBC equity numbers.  As best I can gather, the eventual amount would have been around $4.3 million, although some of that was [[GMP Reduction]] which hadn't accumulated yet.
+
 
+
*Providence groups - $1.4 million (presumably actually the $1,466,227 from INAC).  This matches what one of the MLAs said a couple of years back, and also the press briefing from the Community Agreement ("$63,000" would be $1.4 million x 4.5% return).
+
 
+
*Atcon - $2.3 million target (ballpark $500K paid in) - has Atcon (or its estate) actually been settled with completely?
+
 
+
*Gamble - $300,000 ($150,000 paid in via GMP reduction) - Gamble was quoted in the media that their settlement included $150,000 each to pay out the equity stake.  Were GMP reductions anticipated to have brought them to $300,000 each?  Otherwise the total anticipated equity would have been $4 million, not $4.3.
+
*Jivkov - $300,000 ($150,000 paid in via GMP reduction)
+
 
+
== Older assumptions ==
+
* <s>there's no update on [[Annual Operating Costs|annual bridge O&M]] costs, another few hundred thousand annually.Transportation indicates $60-80,000 annually for "''snow clearance, maintenance, inspections.''".  The DCBC was going to get an indexed $600,000 annually for O&M, and although I assume it was well padded, there must be some DCBC planned costs that aren't in that $60-80K figure.  Some of it may be efficiencies and economies of scale now that Transportation is doing the work, and perhaps some of the insurance costs are offloaded over to Finance, but I really don't know.  I'm not sure if any sort of breakdown of the $600K was ever published (although I'll dig back through the Concession docs).</s>  <b><i>Going back to Transportation's $350,000 for now.</i></b>
+
 
+
*<s> By the letter of the [[Community Opportunities and Involvement Agreement]], Fort Providence should stop receiving their $8000/month [[Involvement Grant]] after the final March 2012 payment.  But since the bridge won't be in operation, there will be no $200,000 annual [[Opportunities Grant]] on April 1 - the 35-year period would be pushed back to 2013.  But I have been unable to confirm this, and one suspects there is a good chance something will be done to keep money of some sort flowing to Fort Providence during the delay.</s>  <b><i>Confirm delay on Opp Grant, but Involvement Grant may be extended.</i></b>
+
 
+
* <s>there's no information available on possible costs or commitments to '''environmental rehab commitments''', which would be outside the construction budget.</s> DoT has submitted a plan to DFO, and costing will await its approval, apparently paid for outside the construction budget.  I actually found some old DCBC documentation ([http://www.mvlwb.ca/mv/Registry/2004/MV2004X0020/MV04X20%20Fisheries%20Act%20Authorization%20May.06-08.pdf 1], [http://www.mvlwb.ca/mv/Registry/2004/MV2004X0020/MV04X20%20Fisheries%20Act%20Authorization%20Amendment%20Jun17-08.pdf 2]) that indicated they were required to set up an $800,000 escrow agreement for this, and that the DCBC "<i>project budget includes funds for the required mitigation and compensation measures.</i>".  It looks like this item has effectively moved from inside to outside the construction budget.
+
 
+
*<s>'''Budget''' - there's no newer details on the construction budget (now around $192 million) since the original 2010 package that was released.  Specifically, there's no guidance on what the various contractor claims and GNWT counter-claims are, and the likely net result (if any) to the construction budget.</s>
+

Latest revision as of 19:18, 22 April 2013

There was a list of outstanding work on the bridge submitted to the Assembly, but it looks like it is all covered either by the construction budget/holdbacks or the NB $13 million fund.

Current

  • Is the "current project budget" still at $202 million?
  • Atcon $1.3 million settlement payment - covered by project budget? I'd assume so, like the Gamble/Jivkov settlement.
  • Atcon deficiencies - current spend ($6.5 million?) and upcoming work ($3-5 million?)
  • Fish Habitat Compensation Plan - any costs estimates?
  • Average annual O&M still around $350,000?
  • Average annual toll collection costs around $300,000?
  • Any numbers on toll traffic?